View Single Post
  #8   Report Post  
Old February 7th 07, 09:13 AM posted to uk.transport.london
Tom Page Tom Page is offline
external usenet poster
 
First recorded activity at LondonBanter: Oct 2005
Posts: 24
Default DLR in Stratford

On 6 Feb, 15:33, "alex_t" wrote:
from inside the main building your view is relaly
just of a jumble of scafolding, and from the track you can see that no
rails have yet been connected from the main track to the new
platforms


Yep, I see that everyday. It looks like they won't finish it even in
February...
I wonder, what's going on here - they did not do much in mid-2006,
then suddenly started quick construction works, and now there seems to
be some kind of pause again...


I know next to nothing about construction, but I imagine the amount of
work one can see happening is not always proportional to the actual
work that's going on - some stages like wiring, inspection, approval
probably are less visible, but still crucial. Let's see what happens...