Stratford - new DLR platforms
In article om, Harry
G writes
First of the new platforms will open Monday 18 June, with the other to
follow in the Autumn.
I went past it this morning. It would appear that they've installed
points in the line so that trains can be routed into the southern
platform. Once that's in use, the track into the existing platform will
be slewed to meet that in the northern of the new platforms.
In diagrammatic form:
Now:
-----------\
###New### \
--------- \
\
---------------*-------- to Pudding Mill Lane
###Old###
After the new one opens:
-----------\
###New### \
----------\ \
\ \
--------- \--*-------- to Pudding Mill Lane
###Old###
--
Clive D.W. Feather | Home:
Tel: +44 20 8495 6138 (work) | Web: http://www.davros.org
Fax: +44 870 051 9937 | Work:
Please reply to the Reply-To address, which is:
|