![]() |
Cost of big and small tubes
I have been told that the cost of making new tube tunnels depends on their
size, with Crossrail-style NR-standard tunnels being more expensive than classic LU-style tube tunnels. Is that true? If so, why, and how big is the difference? I can see why it might be greater - there's more mass to shift, more surface to line - but not massively greater. If it's only a bit more expensive, wouldn't it have made sense to build the underground to be compatible with the rest of the network, as, AIUI, in Tokyo? Thanks, tom -- forget everything from school -- you are programmer |
Cost of big and small tubes
Tom Anderson writes:
I have been told that the cost of making new tube tunnels depends on their size ... Well, sure. There's more mass to shift, and more surface to line. I can see why it might be greater - there's more mass to shift, more surface to line ... There, see? :-) A further issue is that in some cases only a small tube may be able to fit into a narrow vertical or horizontal space between existing obstacles -- either older tunnels or other underground structures, or geological strata that you really don't want to have to tunnel through. A large tunnel, if possible at all, would then incur special costs due to moving the existing structures or tunneling through the difficult terrain. but not massively greater. Typically that's true. I don't have numbers. If it's only a bit more expensive, wouldn't it have made sense to build the underground to be compatible with the rest of the network...? Only if you think it's sensible for through services to be able to operate between them using main line rolling stock, or for main line rolling stock to be usable on the Underground even in the absence of through services. Historically, the subsurface lines (District, Hammersmith & City, Metropolitan, etc.) *were* considered as an extension of the main-line railway network, were built for compatibility with it, and were served by through trains using main-line rolling stock. But later management saw the inter-working as a source of problems and found it preferable to treat these lines as a separate sort of thing; main-line connections at Ealing Broadway, Kensington (Olympia), Paddington, King's Cross, St. Pancras, Farringdon, Liverpool Street, Shoreditch, New Cross, New Cross Gate, and other points I can't remember offhand were all taken out of regular service, and in most cases the connecting tracks were eventually lifted. The tube lines, on the other hand, are descended ultimately from the Tower Subway of 1870, the little cable-operated line whose tunnel diameter was only about 6'8". When you compare a tunnel *that* size to a tunnel of 16' or more to carry main-line stock, the incremental costs don't look so small! The promoters of the Tower Subway planned their second line to be slightly larger, using 8' tubes; after the Tower Subway failed, they suspended the proposal, then eventually upgraded it to the longer and larger line that opened in 1890 as the City & South London Railway, using a tube diameter of 10'2". This was still viewed as a self- contained line for local traffic, so there was no strong reason for compatibility. In fact, it was going to be cable-hauled until late in the construction period. It was found that the C&SLR trains were inconveniently small; the next few tubes, opened from 1898 to 1907, mostly chose slightly larger diameters and this gave rise to today's standard, while the the C&SLR was enlarged to a compatible tunnel size at considerable cost and inconvenience. But it wasn't until the suburban extensions of the 1930s that people really started thinking of tube train routes of the length that now exist, and by then the small size was pretty much locked in. -- Mark Brader "You have seen this incident, based on Toronto sworn testimony. Can you prove that it didn't happen?" -- Plan 9 from Outer Space My text in this article is in the public domain. |
Cost of big and small tubes
Tom Anderson wrote:
I have been told that the cost of making new tube tunnels depends on their size, with Crossrail-style NR-standard tunnels being more expensive than classic LU-style tube tunnels. Is that true? If so, why, and how big is the difference? I can see why it might be greater - there's more mass to shift, more surface to line - but not massively greater. I think you may not have seen the actual figures. AFAIK these are external tunnel dimensions (from Crossrail documents): Victoria Line: 3.81m (older tube tunnels are slightly smaller) Jubilee Line extension: 4.35m diameter Crossrail: 6m diameter Volume to excavate per metre of tunnel: Victoria: 11.4m³ Jubilee: 14.9m³ Crossrail: 28.3m³ Surface area to line per metre of tunnel: Victoria: 12.0m² Jubilee: 13.7m² Crossrail: 18.9m² If it's only a bit more expensive, wouldn't it have made sense to build the underground to be compatible with the rest of the network, as, AIUI, in Tokyo? London was the first city with deep-level tubes; the technology was in its infancy, and a 12-foot diameter tunnel was probably as big as could be managed at the time. Cost and the need for interconnections (e.g. Victoria Line trains to Acton Works for major engineering work) were factors which inhibited a subsequent change to mainline gauge. -- Richard J. (to e-mail me, swap uk and yon in address) |
Cost of big and small tubes
Tom Anderson wrote:
I have been told that the cost of making new tube tunnels depends on their size, with Crossrail-style NR-standard tunnels being more expensive than classic LU-style tube tunnels. Is that true? If so, why, and how big is the difference? I can see why it might be greater - there's more mass to shift, more surface to line - but not massively greater. If it's only a bit more expensive, wouldn't it have made sense to build the underground to be compatible with the rest of the network, as, AIUI, in Tokyo? At the time the tube lines were envisaged I don't think there was any idea of getting them anywhere near the main lines. The sub-surface lines can accomodate main line gauge stock although it does get a bit tight in places with modern stock. In 1982 a test run was carried out with two battery locos and a BR Mk2 coach. It got round the Circle although it did touch in a couple of places. This was in preparation for passenger workings using ex-Met loco No12 Sarah Siddons. In the event these workings were limited to the Met Main to Amersham and Uxbridge. Sorry can't be certain where the southern reversal point was, but I think Wembley Park. Until 1939 there was a through working between Ealing Broadway and Southend using London Tilbury & Southend Railway rolling stock. Haulage from Ealing to Barking was by electric loco and from there by LTS steam loco. Prior to WW1 a number of main line companies provided services over the Metropolitan and Metropolitan District Railways. |
Cost of big and small tubes
Richard J.:
London was the first city with deep-level tubes; the technology was in its infancy, and a 12-foot diameter tunnel was probably as big as could be managed at the time... I don't think there was any technical problem with a larger tunnel; it just wasn't considered commercially necessary. Remember, the Great Northern & City opened in 1904, just 14 years after the City & South London, with 16' tubes intended for main line trains (which, in the end, did not arrive until 1976). -- Mark Brader "People with whole brains, however, dispute Toronto this claim, and are generally more articulate in expressing their views." -- Gary Larson My text in this article is in the public domain. |
Cost of big and small tubes
"Richard J." wrote in message
... Tom Anderson wrote: I can see why it might be greater - there's more mass to shift, more surface to line - but not massively greater. I think that nowadays these seem to be a relatively small part of the cost of building a railway. I think you may not have seen the actual figures. AFAIK these are external tunnel dimensions (from Crossrail documents): Victoria Line: 3.81m (older tube tunnels are slightly smaller) Jubilee Line extension: 4.35m diameter Crossrail: 6m diameter Volume to excavate per metre of tunnel: Victoria: 11.4m³ Jubilee: 14.9m³ Crossrail: 28.3m³ Surface area to line per metre of tunnel: Victoria: 12.0m² Jubilee: 13.7m² Crossrail: 18.9m² Something else worth considering is that a crossover cavern has to have more than twice the radius of the running tunnels, and four times the cross-sectional area. For Crossrail in particular the crossover caverns would be, well, cavernous, and the potential for surface disruption above such a large void is significant. This is why there were going to be no crossovers or sidings in the tunnel section at all, although apparently TPTB have now changed their minds about this. Another thing worth mentioning is that most of the UndergrounD was deliberately built beneath public highways in order to avoid wayleave payments to landowners. This meant putting the two tunnels on top of each other in many places, especially around corners. The impact of tunnel size should be obvious. Further to one of Mark Brader's points, when Crossrail 2 (aka Chelsea Hackney) was planned to be tube gauge it was planned to have a station at Piccadilly Circus. When the plan changed to mainline gauge, this station was deleted from the plan because there is not enough room in that area for the larger platform tunnels that a mainline gauge line would need. -- John Rowland - Spamtrapped Transport Plans for the London Area, updated 2001 http://www.geocities.com/Athens/Acro...69/tpftla.html A man's vehicle is a symbol of his manhood. That's why my vehicle's the Piccadilly Line - It's the size of a county and it comes every two and a half minutes |
Cost of big and small tubes
John Rowland:
Something else worth considering is that a crossover cavern has to have more than twice the radius of the running tunnels, and four times the cross-sectional area. Well, that's true if the crossover is placed in a cylindrical cavern and the two through tracks are straight and, immediately beyond the cavern, in separate single-track tunnels. If making a crossover cavern that size is a major problem, other geometries are possible. For example, trains of moderate speed can have tracks spaced close enough to use a single twin-track tunnel smaller than twice the diameter of a single-track tunnel, and crossovers can fit within this. Another option is step-plate junctions at each end of the crossover. Another option is non-cylindrical tunnels, with stronger lining as needed. Another thing worth mentioning is that most of the UndergrounD was deliberately built beneath public highways in order to avoid wayleave payments to landowners. Indeed, in the early days it wasn't even legal to tunnel under someone else's private property; you had to buy it outright. My impression from what I've read is that this changed between 1890 and about 1900, but I don't know exactly when. -- Mark Brader "Could you please continue the petty bickering? Toronto I find it most intriguing." -- Data ("Haven", ST:TNG, Tracy Torme) My text in this article is in the public domain. |
Cost of big and small tubes
Tom Anderson wrote:
wouldn't it have made sense to build the underground to be compatible with the rest of the network, as, AIUI, in Tokyo? Digressing a bit, I've always wondered why the South coast of England (mainly the South East) uses the 700V DC "third rail" system for electrical power, when the entire rest of the UK uses the 25000V AC overhead cable system. Wouldn't it make more sense to have the same used all over the UK? It means that a lot of national-running trains have to be diesel. -- "We are now approaching Paisley Gilmour Street" |
Cost of big and small tubes
One of the books about the tube (can't remember which) talks about the cost of tunnelling being proportional to the square of the diameter of the bore. This may concur with Richard J's figures below? "Richard J." wrote in message ... Tom Anderson wrote: I have been told that the cost of making new tube tunnels depends on their size, with Crossrail-style NR-standard tunnels being more expensive than classic LU-style tube tunnels. Is that true? If so, why, and how big is the difference? I can see why it might be greater - there's more mass to shift, more surface to line - but not massively greater. I think you may not have seen the actual figures. AFAIK these are external tunnel dimensions (from Crossrail documents): Victoria Line: 3.81m (older tube tunnels are slightly smaller) Jubilee Line extension: 4.35m diameter Crossrail: 6m diameter Volume to excavate per metre of tunnel: Victoria: 11.4m³ Jubilee: 14.9m³ Crossrail: 28.3m³ Surface area to line per metre of tunnel: Victoria: 12.0m² Jubilee: 13.7m² Crossrail: 18.9m² |
Cost of big and small tubes
AyrAlex wrote:
Tom Anderson wrote: wouldn't it have made sense to build the underground to be compatible with the rest of the network, as, AIUI, in Tokyo? Digressing a bit, I've always wondered why the South coast of England (mainly the South East) uses the 700V DC "third rail" system for electrical power, when the entire rest of the UK uses the 25000V AC overhead cable system. Wouldn't it make more sense to have the same used all over the UK? It means that a lot of national-running trains have to be diesel. I know little of the history of the Southern Railway, but I believe that it was decided to let the electrification, parts of which were done back in the time of Yerkes, to proceed apace - IIRC this electrification contributed to the sparse tube coverage in South London. Besides, wasn't 25kVAC thought up well after 700V DC anyway? Brad |
Cost of big and small tubes
Thanks for everyone's answers so far, by the way.
On Wed, 26 May 2004, John Rowland wrote: "Richard J." wrote in message ... Tom Anderson wrote: I can see why it might be greater - there's more mass to shift, more surface to line - but not massively greater. I think that nowadays these seem to be a relatively small part of the cost of building a railway. Precisely! I suppose the meta-answer is that when the tubes were built, through running wasn't on the radar, so there was no point in building them bigger. However, i do suspect that - where the constraints of the geology and other subterranean structures permit - new lines ought to be built to mainline gauge; the relative marginal cost is small, i think, and the options it gives us for the future are large. Further to one of Mark Brader's points, when Crossrail 2 (aka Chelsea Hackney) was planned to be tube gauge it was planned to have a station at Piccadilly Circus. When the plan changed to mainline gauge, this station was deleted from the plan because there is not enough room in that area for the larger platform tunnels that a mainline gauge line would need. Constraints like this. Yes, i think the lure of a station at Piccadilly Circus would be enough to convert me to tube gauge here! tom -- drank lots of pints of beer, usually grolsch/met friends/museums/watch tele/read papers/thought a lot/walked much/much tube (no accidents)/some burgers/some pizza/some resturants (the ones I could afford)/some english breakfasts/some puddings -- Dor Zaf, 15 days in the UK |
Cost of big and small tubes
"Alex":
Digressing a bit, I've always wondered why the South coast of England (mainly the South East) uses the 700V DC "third rail" system for electrical power, when the entire rest of the UK uses the 25000V AC overhead cable system. Wouldn't it make more sense to have the same used all over the UK? In principle yes, but the Southern network is already pressing the limit of what is economical as regards both distance and speed for third-rail trains. Most systems that use it don't have journeys anywhere near as long as London to Bournemouth or Dover. Low-voltage power requires frequent substations due to voltage drop, and the amount of current that can be conveyed is also limited. And if it's DC, it additionally requires AC-to-DC conversion at every substation. Besides, wasn't 25kVAC thought up well after 700V DC anyway? Which completes the story. -- Mark Brader, Toronto | "When you're up to your ass in alligators, maybe | you're in the wrong swamp." -- Bill Stewart My text in this article is in the public domain. |
Cost of big and small tubes
On Wed, 26 May 2004 16:43:32 +0000 (UTC), TheOneKEA
wrote: I know little of the history of the Southern Railway, but I believe that it was decided to let the electrification, parts of which were done back in the time of Yerkes, to proceed apace - IIRC this electrification contributed to the sparse tube coverage in South London. Besides, wasn't 25kVAC thought up well after 700V DC anyway? This last point is the key to it. The technology to make 25kV possible, in particular the ability to convert the AC supply to a much lower voltage DC on board a train, only really became available from around 1945 onwards. A lot of the former Southern Railway was electrified much earlier than this. Converting it from 3rd rail to the overhead system would have been very expensive - almost as expensive as electrifying it from scratch. Martin |
Cost of big and small tubes
In article ,
Piccadilly Pilot wrote: The sub-surface lines can accomodate main line gauge stock although it does get a bit tight in places with modern stock. In 1982 a test run was carried out with two battery locos and a BR Mk2 coach. It got round the Circle although it did touch in a couple of places. This was in preparation for passenger workings using ex-Met loco No12 Sarah Siddons. In the event these workings were limited to the Met Main to Amersham and Uxbridge. Sorry can't be certain where the southern reversal point was, but I think Wembley Park. ISTR it was first done (in recent times anyway) with the BR Track Testing Coach when it was hired by LU, and it was the success of that that led to the idea of railtours. That was the public version anyway ! One such tour was the Battery Rover, which took battery locos along the Met and District parts of the Circle with a train of Mk2 aircons. Nick -- "And we will be restoring normality just as soon as we are sure what is neurotypical anyway. Thank you". -- not quite DNA |
Cost of big and small tubes
AyrAlex (AyrAlex) wrote in message news:f%0tc.51$YT4.7@newsfe5-win...
Tom Anderson wrote: wouldn't it have made sense to build the underground to be compatible with the rest of the network, as, AIUI, in Tokyo? Digressing a bit, I've always wondered why the South coast of England (mainly the South East) uses the 700V DC "third rail" system for electrical power, when the entire rest of the UK uses the 25000V AC overhead cable system. Wouldn't it make more sense to have the same used all over the UK? It means that a lot of national-running trains have to be diesel. No , they could be dual voltage like the Thameslink trains or WAGN services to Moorgate. Also 750V 3rd rail is used up in Merseyside too. Bear in mind however that outside of the southeast , merseyside and strathclyde regions, only a small percentage of the local lines are electrified by any means and even the midland mainline to nottingham and derby is still diesel powered past Bedford. B2003 |
Cost of big and small tubes
On Wed, 26 May 2004 13:31:53 +0100, AyrAlex
(AyrAlex) wrote: It means that a lot of national-running trains have to be diesel. Or be multi-voltage, as most modern electric trains (at least potentially) are - Electrostar, Desiros, 319s, 365s, EMUs Silverlink and WAGN use in London, Eurostars. I can't think of any services which are diesel because of the two electrification systems. They are diesel simply because of a lack of electrification. -- Arthur Figgis Surrey, UK |
Cost of big and small tubes
It means that a lot of national-running trains have to be diesel.
Or be multi-voltage, as most modern electric trains (at least potentially) are - Electrostar, Desiros, 319s, 365s, EMUs Silverlink and WAGN use in London, Eurostars. I can't think of any services which are diesel because of the two electrification systems. They are diesel simply because of a lack of electrification. I can think of some which used to run: the North-West to Brighton services via the Trent Valley and the WLL. |
Cost of big and small tubes
James wrote:
It means that a lot of national-running trains have to be diesel. Or be multi-voltage, as most modern electric trains (at least potentially) are - Electrostar, Desiros, 319s, 365s, EMUs Silverlink and WAGN use in London, Eurostars. I can't think of any services which are diesel because of the two electrification systems. They are diesel simply because of a lack of electrification. I can think of some which used to run: the North-West to Brighton services via the Trent Valley and the WLL. Which electrification system is used on the WLL? |
Cost of big and small tubes
Piccadilly Pilot wrote:
James wrote: It means that a lot of national-running trains have to be diesel. Or be multi-voltage, as most modern electric trains (at least potentially) are - Electrostar, Desiros, 319s, 365s, EMUs Silverlink and WAGN use in London, Eurostars. I can't think of any services which are diesel because of the two electrification systems. They are diesel simply because of a lack of electrification. I can think of some which used to run: the North-West to Brighton services via the Trent Valley and the WLL. Which electrification system is used on the WLL? 750V DC 3rd rail from Clapham Junction to (IIRC) Mitre Bridge Junction, where it becomes 25KV AC overhead. -- Richard J. (to e-mail me, swap uk and yon in address) |
Cost of big and small tubes
Richard J. wrote:
Piccadilly Pilot wrote: James wrote: It means that a lot of national-running trains have to be diesel. Or be multi-voltage, as most modern electric trains (at least potentially) are - Electrostar, Desiros, 319s, 365s, EMUs Silverlink and WAGN use in London, Eurostars. I can't think of any services which are diesel because of the two electrification systems. They are diesel simply because of a lack of electrification. I can think of some which used to run: the North-West to Brighton services via the Trent Valley and the WLL. Which electrification system is used on the WLL? 750V DC 3rd rail from Clapham Junction to (IIRC) Mitre Bridge Junction, where it becomes 25KV AC overhead. Sorry, used "is" when I meant "was" in the context of the previous posters observation about services between the North-West and Brighton. |
Cost of big and small tubes
Piccadilly Pilot wrote:
Richard J. wrote: Piccadilly Pilot wrote: James wrote: It means that a lot of national-running trains have to be diesel. Or be multi-voltage, as most modern electric trains (at least potentially) are - Electrostar, Desiros, 319s, 365s, EMUs Silverlink and WAGN use in London, Eurostars. I can't think of any services which are diesel because of the two electrification systems. They are diesel simply because of a lack of electrification. I can think of some which used to run: the North-West to Brighton services via the Trent Valley and the WLL. Which electrification system is used on the WLL? 750V DC 3rd rail from Clapham Junction to (IIRC) Mitre Bridge Junction, where it becomes 25KV AC overhead. Sorry, used "is" when I meant "was" in the context of the previous posters observation about services between the North-West and Brighton. Others may know the history better than me. AFAIK the southern section from Clapham Junction to Olympia was electrified (3rd rail DC) some time between 1960 and 1990. The northern section from Olympia to Willesden Junction was electrified early in the 20th century (3rd/4th rail DC), but I don't know if that survived the post-war years. The current scheme, with 3rd rail to Mitre Bridge Junction, and 25kV AC north of there, dates from 1992, and was originally installed to support Eurostar. -- Richard J. (to e-mail me, swap uk and yon in address) |
Cost of big and small tubes
On Sat, 29 May 2004 23:39:59 GMT, "Richard J."
wrote: Piccadilly Pilot wrote: Richard J. wrote: Piccadilly Pilot wrote: James wrote: It means that a lot of national-running trains have to be diesel. Or be multi-voltage, as most modern electric trains (at least potentially) are - Electrostar, Desiros, 319s, 365s, EMUs Silverlink and WAGN use in London, Eurostars. I can't think of any services which are diesel because of the two electrification systems. They are diesel simply because of a lack of electrification. I can think of some which used to run: the North-West to Brighton services via the Trent Valley and the WLL. Which electrification system is used on the WLL? 750V DC 3rd rail from Clapham Junction to (IIRC) Mitre Bridge Junction, where it becomes 25KV AC overhead. Sorry, used "is" when I meant "was" in the context of the previous posters observation about services between the North-West and Brighton. Others may know the history better than me. AFAIK the southern section from Clapham Junction to Olympia was electrified (3rd rail DC) some time between 1960 and 1990. I don't think so. Electrification of this section was in the mid 90s. no? Rob. -- rob at robertwoolley dot co dot uk |
Cost of big and small tubes
|
All times are GMT. The time now is 04:14 AM. |
Powered by vBulletin®
Copyright ©2000 - 2025, Jelsoft Enterprises Ltd.
Copyright ©2004-2006 LondonBanter.co.uk