![]() |
Bakerloo Line Stock
Dear All
I thought that you might the following of interest that I received from the dreaded Metronet It has long been known that the the Bakerloo Line is to the last for new trains What worries me is the the lack of clear plans for further refurbishment work or improvements to the 1972 stock used on this line. What about plans plans for -dot matrix in carriages -improved ventilation Any thoughts about -other improvements that should be sort ? -how passengers might campaign ? Best wishes Neil ---------------------------------------------------------------------------- Dear Cllr Nerva We met briefly at the Labour Party Conference in Brighton. You had an enquiry relating to the Bakerloo line rolling stock upgrade. Metronet plans to deliver a Line Upgrade for the Bakerloo Line in 2019 with new rolling stock and signalling, a year in advance of the required London Underground (LU) implementation date. This will include a new fleet of 42 x 7 car trains. All the current signal equipment will be replaced with ATP Distance To Go Signalling for the length of line owned by LU. This will deliver the LU capability enhancement requirements as specified by LU in the PPP Contract. Our maintenance regime will ensure that the existing rolling stock and signalling system has sufficient residual life to safely supply London Underground with the required capability and service levels until the latest implementation date of March 2020. The Bakerloo Line rolling stock entered service in 1972 and was given a major overhaul and modernisation between 1991 - 1995. There are a number of projects ongoing to improve the performance and appearance of the Bakerloo line which has been running well within the benchmark set out by the PPP Contract. These projects have enabled LUL to run additional trains during the peak and off peak services, improving train availability for the travelling public. Deep cleans and enhanced cleaning programmes for trains and stations, coupled with Metronet's continued commitment to zero tolerance of graffiti have all improved the public's perception of the cleanliness and condition of assets on the Bakerloo Line. Metronet continues to seek and target improvements to all aspects of the Bakerloo line to improve asset reliability, ultimately allowing LU to provide a faster and more efficient railway. Some of the current initiatives in support of this aim a · Overhaul of Bakerloo Line fleet doors to reduce failures in service and support other initiatives in increasing overall line capability · Ongoing condition improvements to large sections of the Bakerloo Line track ultimately to reduce failures but also to remove noise complaints and prolong the life of the assets. Across the Bakerloo, Central and Victoria lines we aim to renew 16.5km of track in the 05/06 financial year, which come to an end 31 March 2006. If you have any other questions or issues to raise, please do contact me. |
Bakerloo Line Stock
On 16 Oct 2005 08:01:49 -0700, "cllr neil nerva - brent council -
london" wrote: Metronet plans to deliver a Line Upgrade for the Bakerloo Line in 2019 So we might get it by 2025, if we're lucky. -- James Farrar . @gmail.com |
Bakerloo Line Stock
Metronet plans to deliver a Line Upgrade for the Bakerloo Line in 2019
with new rolling stock and signalling, a year in advance of the required London Underground (LU) implementation date. A whole year? Wow! Does anyone find it funny that some people will religiously change their car after 12-36 months, while these trains will be FORTY SEVEN years old when they finally get replaced? I presume they must be getting another refurbishment in that time? The Victoria/Bakerloo interior is pretty good, but it won't last another 14 years! Information screens are a must I would have thought - and something to be added now, not in 2019. Jonathan |
Bakerloo Line Stock
wrote: Does anyone find it funny that some people will religiously change their car after 12-36 months, while these trains will be FORTY SEVEN years old when they finally get replaced? 47 years is barely run in. The previous Bakerloo stock is still going strong in the Isle of Wight, almost 70 years old. Chris |
Bakerloo Line Stock
|
Bakerloo Line Stock
|
Bakerloo Line Stock
|
Bakerloo Line Stock
|
Bakerloo Line Stock
Paul Corfield wrote:
On 16 Oct 2005 11:47:27 -0700, wrote: I presume they must be getting another refurbishment in that time? The Victoria/Bakerloo interior is pretty good, but it won't last another 14 years! Information screens are a must I would have thought - and something to be added now, not in 2019. If there is another upgrade then it would involve the provision of customer info displays etc. I shall need to check if one is included in the BCV contract or not. There's nothing about refurbishment of the current fleet on the page of Metronet's website devoted to their plans for the Bakerloo. http://www.metronetrail.com/default....=1078650771772 -- Richard J. (to e-mail me, swap uk and yon in address) |
All times are GMT. The time now is 07:02 AM. |
Powered by vBulletin®
Copyright ©2000 - 2025, Jelsoft Enterprises Ltd.
Copyright ©2004-2006 LondonBanter.co.uk