![]() |
Evergreen 2
Right,
Quick question - who paid for Evergreen 2? Am i right in thinking it was Chiltern (or Chiltern's investors, or banks lending to Chiltern, or something to that effect)? Not the government? And that presumably Chiltern thought they could make enough from fares (and perhaps increased subsidy) from the extra trains to cover it? Anyone know how that's working out so far? tom -- I only listen to mashups of The Carpenters and ear-bleeding German gabber -- boomaga |
Evergreen 2
"Tom Anderson" wrote in message h.li... Right, Quick question - who paid for Evergreen 2? Am i right in thinking it was Chiltern (or Chiltern's investors, or banks lending to Chiltern, or something to that effect)? Not the government? And that presumably Chiltern thought they could make enough from fares (and perhaps increased subsidy) from the extra trains to cover it? Anyone know how that's working out so far? Chiltern's parent company Laing paid for it to be built, but with a loan backed by Network Rail IIRC, which meant Laing had the financial risk during the project; and I believe when it was complete it was then transferred to Network Rail for an agreed sum. I think it is called a 'Design, Build, Finance and Transfer' DBFT arrangement... There seem to have been a few false starts with new timetabling to make use of the new capacity, though - there was a lot of correspondence with passenger groups on their website a couple of months back... Paul |
Evergreen 2
On Fri, 11 May 2007, Paul Scott wrote:
"Tom Anderson" wrote in message h.li... Quick question - who paid for Evergreen 2? Chiltern's parent company Laing paid for it to be built, but with a loan backed by Network Rail IIRC, which meant Laing had the financial risk during the project; and I believe when it was complete it was then transferred to Network Rail for an agreed sum. I think it is called a 'Design, Build, Finance and Transfer' DBFT arrangement... Aha. So in effect, NR paid for it, but only after it was built, and for a fixed price, so Laing took the risk of going over schedule and over budget. Except a loan backed by NR sounds like if it all went (or goes?) tits-up, they end up footing the bill anyway! Hmm. So it doesn't really represent private sector investment in the network. Oh - unless the amount NR paid for it was less than it (was planned to) cost, in which case it's shared. Anyone know how that's working out so far? There seem to have been a few false starts with new timetabling to make use of the new capacity, though - there was a lot of correspondence with passenger groups on their website a couple of months back... I know nothing about Chiltern's market, but do they think they'll be able to pull in more passengers once this is done? tom -- Vive la chimie, en particulier, et la connaissance en general. -- Herve This |
Evergreen 2
Tom Anderson wrote:
I know nothing about Chiltern's market, but do they think they'll be able to pull in more passengers once this is done? The December timetable change was the first to take advantage of completion of the new works under Project Evergreen Phase 2 (two additional platforms at Marylebone, plus a stabling siding to replace those being lost; relocation of servicing facilities from adjacent to Marylebone to the new light maintenance depot at Wembley; shortened signalling sections and additional signalling and changes from two-aspect to three-aspect and from three-aspect to four-aspect at various points along the route, particularly between High Wycombe and Bicester and between Princes Risborough and Aylesbury) but there are some tweaks to that timetable, in the light of operating experience, being introduced next week with the summer timetable. The changes give additional capacity at Marylebone, meaning that trains can be at the platform for longer (eliminating many of the short turnarounds that were annoying passengers, by only giving them five minutes or more to sprint from the concourse to the train) and that more platforms are available to handle trains when things go awry. The additional signalling means that trains can run closer together, thus allowing additional trains to be run. On many services this was becoming necessary due to the booming number of passengers - but the infrastructure was not in place to allow additional trains to run. From projected figures this was looking to become a problem and Chiltern Railways, John Laing and Network Rail acted proactively to provide the capacity - unlike in several other areas of the country where pricing passengers away seems to be the accepted action. At the Network SouthEast launch of the modernised Chiltern network in 1990 the line was operating a total of 89 passenger vehicles (28 two-car trains and 11 three-car). By privatisation this had been reduced to 75 vehicles by the transfer of 7 two-car trains to Thames Trains. Since privatisation the transferred-out trains have returned and an additional 68 vehicles have been added to the fleet (10 four-car trains, 9 three-car trains and the single-car used on the peak hour services between Princes Risborough and Aylesbury). Services have been extended on from Banbury, the former limit of services (one train every two hours) to serve Birmingham (one train every half-hour), Kidderminster (peak hours only) and Stratford-upon-Avon. Passenger numbers have risen significantly over the years and show no signs of abating, hence the need for Project Evergreen. |
All times are GMT. The time now is 05:33 AM. |
Powered by vBulletin®
Copyright ©2000 - 2025, Jelsoft Enterprises Ltd.
Copyright ©2004-2006 LondonBanter.co.uk