Home |
Search |
Today's Posts |
![]() |
|
London Transport (uk.transport.london) Discussion of all forms of transport in London. |
Reply |
|
LinkBack | Thread Tools | Display Modes |
#41
![]() |
|||
|
|||
![]()
On May 17, 3:48 pm, Mr Thant
wrote: On 17 May, 00:56, Mizter T wrote: Not so quick - there is another reason, namely that North Quay will be the worksite for the Crossrail station. The Canary Wharf Group (CWG) can't begin construction of the new office development on North Quay, which already has planning permission, until the Crossrail station box has been finished - which it should be by summer 2012. So the shops aren't the driving force here. Ah, that makes sense. So the station is CWG's 'baby', which perhaps explains the addition of the four floors of retail (is this element really such a late addition though?). Yes. Original design with two separate islands (see drawing page 336):http://billdocuments.crossrail.co.uk...1.Environmenta... Announcement of new design (July 2008):http://www.canarywharf.com/news/ns_news_t.asp?id=344 (it may have always been envisioned something might go in the middle, but certainly it was only as an optional extra) U There's something else big happening in the Stratford area in 2012 (can't immediately think what...) which might feed a desire to get worksites cleared away, retail open etc. Tim |
#42
![]() |
|||
|
|||
![]()
In message
, at 02:49:11 on Sun, 17 May 2009, Mizter T remarked: Do they have to dig the tunnels that connect to the station first, or does the station box come first? The station box, by the looks of it - the construction of which was kicked off on Friday at Canary Wharf (or at least that's what the PR people would have you believe!) . From a construction POV I'd imagine that sequencing the station box first can only make sense - not sure it'd really be possible or at least easy to do it the other way round. I'd have thought it would be easier to drive one TBM through the site (twice if two tunnels) before the box was there. Otherwise you have two disconnected tunnels to bore, and a machine to move from one side of the box to the other. -- Roland Perry |
#43
![]() |
|||
|
|||
![]()
In message , at 13:29:58 on Sun, 17
May 2009, John Rowland remarked: Do they have to dig the tunnels that connect to the station first, or does the station box come first? If they don't want the tunnels to flood, they'd better build the station box first! If they build a tunnel all the way through the site, why would that fill up with water any more than the other bits of tunnel under other docks and the river? Or are you suggesting the tunnel isn't deep enough to be completely under the dock - which would be very odd because the station box is shorter than the dock. -- Roland Perry |
#44
![]() |
|||
|
|||
![]() On May 17, 3:48*pm, Mr Thant wrote: On 17 May, 00:56, Mizter T wrote: Not so quick - there is another reason, namely that North Quay will be the worksite for the Crossrail station. The Canary Wharf Group (CWG) can't begin construction of the new office development on North Quay, which already has planning permission, until the Crossrail station box has been finished - which it should be by summer 2012. So the shops aren't the driving force here. Ah, that makes sense. So the station is CWG's 'baby', which perhaps explains the addition of the four floors of retail (is this element really such a late addition though?). Yes. Original design with two separate islands (see drawing page 336): http://billdocuments.crossrail.co.uk...1.Environmenta... Announcement of new design (July 2008): http://www.canarywharf.com/news/ns_news_t.asp?id=344 (it may have always been envisioned something might go in the middle, but certainly it was only as an optional extra) Thanks for the info. I wonder if CWG's financial support for Crossrail was contingent on being able to hitch this extra development into the Crossrail station... |
#45
![]() |
|||
|
|||
![]() On May 17, 6:22*pm, TimB wrote: On May 17, 3:48 pm, Mr Thant wrote: On 17 May, 00:56, Mizter T wrote: Not so quick - there is another reason, namely that North Quay will be the worksite for the Crossrail station. The Canary Wharf Group (CWG) can't begin construction of the new office development on North Quay, which already has planning permission, until the Crossrail station box has been finished - which it should be by summer 2012. So the shops aren't the driving force here. Ah, that makes sense. So the station is CWG's 'baby', which perhaps explains the addition of the four floors of retail (is this element really such a late addition though?). Yes. Original design with two separate islands (see drawing page 336): http://billdocuments.crossrail.co.uk...1.Environmenta... Announcement of new design (July 2008): http://www.canarywharf.com/news/ns_news_t.asp?id=344 (it may have always been envisioned something might go in the middle, but certainly it was only as an optional extra) There's something else big happening in the Stratford area in 2012 (can't immediately think what...) which might feed a desire to get worksites cleared away, retail open etc. Hmm, whilst "ready by 2012" is the magic phrase in London planning, I can't really see this being particularly connected - I think it's really more to do with dovetailing in with the overall Crossrail construction timetable. |
#46
![]() |
|||
|
|||
![]()
In message , at 12:06:12
on Sat, 16 May 2009, remarked: Having built on every scrap of land they are now building on the old docks - so inconsiderate for someone to have dug them in the first place. Why? It's not as if the docks are required for shipping any more. Having seen some more paperwork, it appears that the docks are also a conservation area. -- Roland Perry |
#47
![]() |
|||
|
|||
![]()
On 17 May, 18:46, Roland Perry wrote:
I'd have thought it would be easier to drive one TBM through the site (twice if two tunnels) before the box was there. Otherwise you have two disconnected tunnels to bore, and a machine to move from one side of the box to the other. Quoth the horse: "The plan is to have the SCL station platform tunnel primary lining completed in advance of the arrival of the running tunnel TBMs. This will allow the tunnel boring machinery to be slid through the completed platform tunnels and re-start the running tunnel drive to the next station." http://billdocuments.crossrail.co.uk... 0Strategy.pdf At Paddington (which is cut-and-cover, not SCL) they are planning to build one of the running tunnels first, so that the earth from digging the station box can be taken away to Royal Oak. At Isle of Dogs there'll be no such shenanigans, as far as I know. U |
#48
![]() |
|||
|
|||
![]() "Paul Corfield" wrote in message ... Hanover Square / Tenterden St behind Oxford St / Oxford Circus is the eastern exit point for Bond St Station. IIRC there is no physical link to Oxford Circus tube station. Only in London could we fail to provide such a link. To provide such an interchange here would probably add so much to the cost of the scheme that it would never happen. I limit my use of Oxford Circus to the cross platform interchanges between the Victoria and Bakerloo lines, and that's bad enough. The thought of adding a load of Crossrail passengers to the scrum doesn't bear thinking about. It would make more sense to add an interchange as part of a (much needed) rebuild of Oxford Circus station, rather than trying to do it as part of Crossrail. David A Stocks |
#49
![]() |
|||
|
|||
![]()
In message
, at 12:36:40 on Sun, 17 May 2009, Mr Thant remarked: "The plan is to have the SCL station platform tunnel primary lining completed in advance of the arrival of the running tunnel TBMs. This will allow the tunnel boring machinery to be slid through the completed platform tunnels and re-start the running tunnel drive to the next station." If that's the new plan, it differs from the one posted earlier today, which describes the kind of discontinuity at the station that I was assuming they would be trying to avoid: "The tunnel drives westwards to Stepney Green are commenced from the crossover area at the western end of the Isle of Dogs station box. Assembly of the TBM will take three months at this location, with the subsequent drive to Stepney Green taking ten months. Additionally, the Isle of Dogs station box will be broken through at its eastern end by a TBM completing its drive from the east, having been launched from the Limmo Peninsula nine months previously. This TBM would then be disassembled within the Isle of Dogs station box." -- Roland Perry |
#50
![]() |
|||
|
|||
![]()
On 17 May, 22:07, Roland Perry wrote:
If that's the new plan, it differs from the one posted earlier today, Yes. They completely rethought the tunnelling strategy after protests, and the crossover at Isle of Dogs has also been removed. The document you quoted is from the original Environmental Statement and hasn't been updated, although they have published four sets of new documents that cover only the changes. The only way to work out what the current plan is for anything to work backwards through all five sets of documents to find the newest one that covers the detail you're interested in (and people wonder why I quit blogging about this stuff). In any case, the tunneling strategy I just linked to is a current one. U |
Reply |
Thread Tools | Search this Thread |
Display Modes | |
|
|
![]() |
||||
Thread | Forum | |||
Investigation under way after Tube train collision | London Transport | |||
BBC - Soho shops make way for Crossrail | London Transport | |||
BBC - Soho shops make way for Crossrail | London Transport | |||
BBC - Soho shops make way for Crossrail | London Transport | |||
the book...London under London | London Transport |