On Jul 7, 11:02*pm, Mizter T wrote:
On Jul 7, 8:01*pm, Paul Corfield wrote: People may be interested to note that the most recent TfL Investment Report - in the TfL Board papers for late last month - shows a target opening date of Monday 20 September 2010 for the Stratford International Line. *If DLR do their usual thing it'll probably open the Saturday or Sunday beforehand. Reading the commentary it looks as if delays mean that is probably a realistic date. Thanks Paul - been intending to ask about this, as the date shown for the opening of the extension on the relevant DLR Development webpage [1] was quietly changed recently (within the last month or two I think) from "Summer 2010" to "Autumn 2012". [1]http://developments.dlr.co.uk/extensions/stratford/whatnext.asp Having gone past the line this morning on a Jubilee Line train it is clear that the stations look close to completion. Signage is installed but covered over, PA and CCTV is installed as are other bits of kit like lighting etc. I expect it will need commissioning and testing but otherwise it's pretty much there. I suspect the next bit is livening up the traction power and signalling and getting it gauge tested and then test running with trains. The one bit I have yet to see is the DLR "international" station - has anyone any idea how this is progressing? -- Paul C via Google |
#2
![]() |
|||
|
|||
![]()
On 21 July, 13:35, Paul Corfield wrote:
On Jul 7, 11:02*pm, Mizter T wrote: On Jul 7, 8:01*pm, Paul Corfield wrote: People may be interested to note that the most recent TfL Investment Report - in the TfL Board papers for late last month - shows a target opening date of Monday 20 September 2010 for the Stratford International Line. *If DLR do their usual thing it'll probably open the Saturday or Sunday beforehand. Reading the commentary it looks as if delays mean that is probably a realistic date. Thanks Paul - been intending to ask about this, as the date shown for the opening of the extension on the relevant DLR Development webpage [1] was quietly changed recently (within the last month or two I think) from "Summer 2010" to "Autumn 2012". [1]http://developments.dlr.co.uk/extensions/stratford/whatnext.asp Having gone past the line this morning on a Jubilee Line train it is clear that the stations look close to completion. Signage is installed but covered over, PA and CCTV is installed as are other bits of kit like lighting etc. I expect it will need commissioning and testing but otherwise it's pretty much there. *I suspect the next bit is livening up the traction power and signalling and getting it gauge tested and then test running with trains. The one bit I have yet to see is the DLR "international" station - has anyone any idea how this is progressing? We caught a train from Stratford International on Saturday evening, I don't know where the DLR station is supposed to be, but there's now hoardings up all over the entrance to International (where the shuttle bus stops) so presumably they've started building access ways to the DLR there. But why didn't they do that when they first built the station? Also does anyone know where at Stratford Regional the new DLR platforms will be? Will they be near the existing DLR or somewhere else completely? -- Roy |
#3
![]() |
|||
|
|||
![]() "Roy Stilling" wrote in message ... Also does anyone know where at Stratford Regional the new DLR platforms will be? Will they be near the existing DLR or somewhere else completely? They are the rebuilt North London Line platforms, between the Jubilee line and the main entrance. Paul S |
#4
![]() |
|||
|
|||
![]()
On 21 July, 14:15, Roy Stilling wrote:
On 21 July, 13:35, Paul Corfield wrote: On Jul 7, 11:02*pm, Mizter T wrote: On Jul 7, 8:01*pm, Paul Corfield wrote: People may be interested to note that the most recent TfL Investment Report - in the TfL Board papers for late last month - shows a target opening date of Monday 20 September 2010 for the Stratford International Line. *If DLR do their usual thing it'll probably open the Saturday or Sunday beforehand. Reading the commentary it looks as if delays mean that is probably a realistic date. Thanks Paul - been intending to ask about this, as the date shown for the opening of the extension on the relevant DLR Development webpage [1] was quietly changed recently (within the last month or two I think) from "Summer 2010" to "Autumn 2012". [1]http://developments.dlr.co.uk/extensions/stratford/whatnext.asp Having gone past the line this morning on a Jubilee Line train it is clear that the stations look close to completion. Signage is installed but covered over, PA and CCTV is installed as are other bits of kit like lighting etc. I expect it will need commissioning and testing but otherwise it's pretty much there. *I suspect the next bit is livening up the traction power and signalling and getting it gauge tested and then test running with trains. The one bit I have yet to see is the DLR "international" station - has anyone any idea how this is progressing? We caught a train from Stratford International on Saturday evening, *I don't know where the DLR station is supposed to be, but there's now hoardings up all over the entrance to International (where the shuttle bus stops) so presumably they've started building access ways to the DLR there. *But why didn't they do that when they first built the station? Also does anyone know where at Stratford Regional the new DLR platforms will be? *Will they be near the existing DLR or somewhere else completely? -- Roy The DLR station is just to the north of where the buses pick you up. |
Reply |
Thread Tools | Search this Thread |
Display Modes | |
|
|
![]() |
||||
Thread | Forum | |||
DLR Stratford International | London Transport | |||
DLR - Stratford International construction contract | London Transport | |||
Work to start on DLR from Canning Town to Stratford International | London Transport | |||
NLL Closure / DLR to Stratford International | London Transport | |||
DLR or Jubilee line extension to Stratford International - two questions | London Transport |