Home |
Search |
Today's Posts |
#1
![]() |
|||
|
|||
![]()
Amongst a number of points covered in SoS Hammond's announcement this
morning was this one: ---quote--- Today, I can confirm we will fund and deliver the Thameslink programme in its entirety, virtually doubling the number of north-south trains running through central London at peak times. But the original programme for the rebuilding of London Bridge was always ambitious, with substantial risks around delivery, and operation of existing services, during construction. To reduce these risks, we have re-profiled the delivery of the programme to achieve completion in 2018. This will enable Network Rail to make further efficiencies to their design and delivery programme. ---/quote--- Source: http://www.dft.gov.uk/press/speeches...ammond20101125 So, it appears as though the whole shebang will go ahead as originally envisaged, i.e. including Key Output 2 (of which the extensive Bermondsey dive-unders on the approaches to London Bridge are a part, for instance). |
#2
![]() |
|||
|
|||
![]()
On Nov 25, 10:37*am, "Mizter T" wrote:
Amongst a number of points covered in SoS Hammond's announcement this morning was this one: ---quote--- Today, I can confirm we will fund and deliver the Thameslink programme in its entirety, virtually doubling the number of north-south trains running through central London at peak times. But the original programme for the rebuilding of London Bridge was always ambitious, with substantial risks around delivery, and operation of existing services, during construction. To reduce these risks, we have re-profiled the delivery of the programme to achieve completion in 2018. *This will enable Network Rail to make further efficiencies to their design and delivery programme. ---/quote--- Source:http://www.dft.gov.uk/press/speeches...ts/hammond2010... So, it appears as though the whole shebang will go ahead as originally envisaged, i.e. including Key Output 2 (of which the extensive Bermondsey dive-unders on the approaches to London Bridge are a part, for instance). Excellent news. And, given the circumstances, surprising. A good day for railways of the UK's Southeast, and especially London. |
#3
![]() |
|||
|
|||
![]()
"Mizter T" wrote:
Amongst a number of points covered in SoS Hammond's announcement this morning was this one: Today, I can confirm we will fund and deliver the Thameslink programme in its entirety, virtually doubling the number of north-south trains running through central London at peak times. But the original programme for the rebuilding of London Bridge was always ambitious, with substantial risks around delivery, and operation of existing services, during construction. To reduce these risks, we have re-profiled the delivery of the programme to achieve completion in 2018. This will enable Network Rail to make further efficiencies to their design and delivery programme. Source: http://www.dft.gov.uk/press/speeches...ammond20101125 So, it appears as though the whole shebang will go ahead as originally envisaged, i.e. including Key Output 2 (of which the extensive Bermondsey dive-unders on the approaches to London Bridge are a part, for instance). This is excellent news, and by far the most satisfying part of today's announcement. The Thameslink project has recently been overshadowed by its more glamorous relative, Crossrail, yet the economic and environmental benefits that Thameslink will deliver to London and the south east are no less significant. There was real concern worry that the high cost of (1) remodelling London Bridge to include additional though platforms and (2) the Bermondsey dive-unders could have caused the project to be curtailed. However, this budgetary problem has been solved by allowing an additional two years to complete the project. This spreads the cost over a greater number of financial years and allows more economic (and less disruptive) methods of construction to be used at London Bridge. All praise to the Thameslink project team who have succeeded in gaining Ministerial approval for the whole of this vital if somewhat unsexy project. |
#4
![]() |
|||
|
|||
![]()
"Richard Hunt" wrote:
Mizter T wrote: So, it appears as though the whole shebang will go ahead as originally envisaged, i.e. including Key Output 2 (of which the extensive Bermondsey dive-unders on the approaches to London Bridge are a part, for instance). Was the original "Thameslink 2000" project, as envisaged, ever completed? It was delayed. Basically, Thameslink 2000 is what we are discussing. |
#5
![]() |
|||
|
|||
![]()
In article ,
Bruce wrote: "Richard Hunt" wrote: It was delayed. Basically, Thameslink 2000 is what we are discussing. Right. It was renamed "The Thameslink Programme" once the delays got so long that the 2000 name was just too emabarassingly silly. -roy |
#6
![]() |
|||
|
|||
![]()
In message , at 10:37:20 on
Thu, 25 Nov 2010, Mizter T remarked: Amongst a number of points covered in SoS Hammond's announcement this morning was this one: ---quote--- Today, I can confirm we will fund and deliver the Thameslink programme in its entirety Does that include the link-up with the GN line to Cambridge, or was that air-brushed from the scheme long ago? istr they were supposed to be lengthening platforms at Cambridge to take 12 cars, but I think they may have changed their mind and are doing an island instead. -- Roland Perry |
#7
![]() |
|||
|
|||
![]() |
#8
![]() |
|||
|
|||
![]()
Anyone know what the plans are for the remaining parts of the moorgate line
are? Will LU take them over eventually? B2003 |
#9
![]() |
|||
|
|||
![]()
In article ,
Bruce wrote: Basically, Thameslink 2000 is what we are discussing. Right. It was renamed "The Thameslink Programme" once the delays got so long that the 2000 name was just too emabarassingly silly. "Thameslink 2018" doesn't have quite the same ring to it. ;-) So basically, we are today celebrating that Thameslink 2000 is only delayed a further two years (now making it 18 years late) rather than actually being cancelled :-/ -roy |
#10
![]() |
|||
|
|||
![]()
In article ,
Roland Perry wrote: istr they were supposed to be lengthening platforms at Cambridge to take 12 cars, but I think they may have changed their mind and are doing an island instead. Cambridge has had 12-car Class 365 services to Kings Cross in the morning peak for some time now. -roy |
Reply |
Thread Tools | Search this Thread |
Display Modes | |
|
|
![]() |
||||
Thread | Forum | |||
Thameslink project (i.e. TL2K) gets legal & planning go-ahead | London Transport | |||
Network Rail asks for extra money to fund Thameslink Programme | London Transport News | |||
Thameslink Programme | London Transport | |||
"Mind the Gap" - Radio programme | London Transport |