#1
![]() |
|||
|
|||
![]()
We are well past the anticipated opening dates which were variously Jan
2011, Feb 2011 and possibly March 2011. Therefore dates like "late Spring" or "early Summer" are now mentioned but you can debate what that means. Just so long as no-one mentions "late Summer"! -roy |
#2
![]() |
|||
|
|||
![]()
In message , Roy Badami
writes We are well past the anticipated opening dates which were variously Jan 2011, Feb 2011 and possibly March 2011. Therefore dates like "late Spring" or "early Summer" are now mentioned but you can debate what that means. Just so long as no-one mentions "late Summer"! I can remember the Jubilee (Fleet) line being finished in a hurry for something or other at Stratford, so important that the moving block signalling was abandoned. Anyone remember what it was? What's the likelihood something will delay the DLR and compromises will be made? -- Clive |
#3
![]() |
|||
|
|||
![]()
In message , Clive
writes I can remember the Jubilee (Fleet) line being finished in a hurry for something or other at Stratford, so important that the moving block signalling was abandoned. Anyone remember what it was? The opening of the millenium dome in North Greenwich, rather than anything at Stratford. There were multiple delays on the Jubilee extension, including escalating costs, lack of promised finance, and worries about the New Austrian Tunnelling Method used. But the full moving block signalling had to be abandoned because it was an untried system developed by Westinghouse, and couldn't be made to work. -- Paul Terry |
#4
![]() |
|||
|
|||
![]()
In message , Paul Terry
writes In message , Clive writes I can remember the Jubilee (Fleet) line being finished in a hurry for something or other at Stratford, so important that the moving block signalling was abandoned. Anyone remember what it was? The opening of the millenium dome in North Greenwich, rather than anything at Stratford. Thank you, I couldn't remember what it was. There were multiple delays on the Jubilee extension, including escalating costs, lack of promised finance, and worries about the New Austrian Tunnelling Method used. Is that the same method, where the tunnel collapsed under Heathrow? But the full moving block signalling had to be abandoned because it was an untried system developed by Westinghouse, and couldn't be made to work. Isn't it moving block on the DLR? Have they got anywhere near getting it working on the Jubilee yet? Did I hear that the Jubilee was to be automatic like the Victoria and Central lines are? -- Clive |
#5
![]() |
|||
|
|||
![]()
"Clive" wrote in message
... Isn't it moving block on the DLR? Have they got anywhere near getting it working on the Jubilee yet? Yes, and Yes - the Jubilee has been using moving block since Christmas, (it's known as the 'transmission based train control system' (TBTC)) , except for the section between Dollis Hill and Stanmore. The conventional signalling is no longer used, which is why it is all covered up. Paul S |
#6
![]() |
|||
|
|||
![]()
In message , Clive
writes In message , Paul Terry writes There were multiple delays on the Jubilee extension, including escalating costs, lack of promised finance, and worries about the New Austrian Tunnelling Method used. Is that the same method, where the tunnel collapsed under Heathrow? Yes, and that's the reason for one of the Jubilee extension delays. But the full moving block signalling had to be abandoned because it was an untried system developed by Westinghouse, and couldn't be made to work. Isn't it moving block on the DLR? The Jubilee contract eventually went to Alcatel, who had provided a workable system for the DLR, but the Jubilee solution was not full moving block (partly because of difficulties integrating with the older signalling on the rest of the Jubilee line). Have they got anywhere near getting it working on the Jubilee yet? I think that most of it is now working. -- Paul Terry |
#7
![]() |
|||
|
|||
![]()
In message , Paul Corfield
writes ITYM North Greenwich not Stratford. I don't doubt you're right, but what was it that the Jubilee line was finished in a hurry for? -- Clive |
Reply |
Thread Tools | Search this Thread |
Display Modes | |
|
|
![]() |
||||
Thread | Forum | |||
Stratford International opening date? | London Transport | |||
Stratford International opening date? | London Transport | |||
TfL Board gives approval for next step for DLR Stratford extension | London Transport | |||
DLR or Jubilee line extension to Stratford International - two questions | London Transport | |||
Oyster Pre-Pay - Does Anyone Have Planned Launch Date | London Transport |