Home |
Search |
Today's Posts |
![]() |
|
London Transport (uk.transport.london) Discussion of all forms of transport in London. |
Reply |
|
LinkBack | Thread Tools | Display Modes |
#12
![]() |
|||
|
|||
![]() |
#13
![]() |
|||
|
|||
![]()
On 30/05/2011 19:32, Mwmbwls wrote:
On May 30, 11:50 am, wrote: They would have to order some more units, but that wouldn't be a problem in the short term. The Class 172 would be leased to another TOC if this were the case and my understanding is that was why they have the internal layout that they do. It was also one of the reasons that they were directly leased from Angel Trains, rather than the more complex ownership history of the class 378s (originally ordered by TfL directly). If the Croxley link came to pass the 172s could be easily redeployed to provide the Watford to Aylesbury shuttle service. No need to change the lease. It would also be possible to outsource the maintenance to Chiltern who operate similar stock. Are there any plans to re-extend Metropolitan service between Amersham and Aylesbury? They were talking at one point, about re-extending the Bakerloo out to Watford Junction, for example. |
#14
![]() |
|||
|
|||
![]() wrote Are there any plans to re-extend Metropolitan service between Amersham and Aylesbury? Very unlikely. There have been two occasions when something of the sort has been considered. In the early 1980s there was serious consideration of closing Marylebone, transferring the Joint Line service to Paddington, and making Aylesbury passengers change at Amersham to a Met train. AIUI a major reason why this was rejected was that the Met couldn't cope with all the passengers who used Met line trains into Marylebone. Later, the first iteration of Crossrail involved a spur to take trains on to the M&SWJ north of Acton Wells, then via new trackage at Neasden on to the "Chiltern" Met Line. There would have been 25 kV OHLE through to Aylesbury, and Crossrail would have taken over the Chiltern Met Line and the Met Amersham and Chesham lines, leaving Baker Street with Watford and Uxbridge. This was rejected largely, AIUI, because there are insufficient passengers from beyond Amersham to Aylesbury to justify electrification. On top of this, TfL, as an emanation of the Mayor of London, only has a very tenuous remit beyond the boundary of Greater London. Peter |
#15
![]() |
|||
|
|||
![]()
"Peter Masson" wrote in message
news ![]() wrote Are there any plans to re-extend Metropolitan service between Amersham and Aylesbury? Very unlikely. There have been two occasions when something of the sort has been considered. In the early 1980s there was serious consideration of closing Marylebone, transferring the Joint Line service to Paddington, and making Aylesbury passengers change at Amersham to a Met train. AIUI a major reason why this was rejected was that the Met couldn't cope with all the passengers who used Met line trains into Marylebone. Later, the first iteration of Crossrail involved a spur to take trains on to the M&SWJ north of Acton Wells... Midland and South Western Junction was nowhere near there :-) The bit north of Acton Wells was Midland only. I must confess I had to look up the North and South Western Junction Joint - it seems to have been the usual "let's get past the Great Western" effort (Midland, LNW and North London). Regards Jonathan |
#16
![]() |
|||
|
|||
![]()
On 30/05/2011 11:47, Paul Corfield wrote:
There are not enough 378s around nor are there any contract options left to be activated. I suspect that by the time comes around to electrify the line that Bombardier will have thrown away the jigs and People often say thrown away jigs will stop rolling stock orders, but what does it actually mean in the contect of modern trains? Won't they just upload computer files to a new jig-o-matic, or something? -- Arthur Figgis Surrey, UK |
#17
![]() |
|||
|
|||
![]()
In article ,
Jonathan Morton wrote: "Peter Masson" wrote in message news ![]() Later, the first iteration of Crossrail involved a spur to take trains on to the M&SWJ north of Acton Wells... Midland and South Western Junction was nowhere near there :-) The bit north of Acton Wells was Midland only. Point of order, this *was* the M&SW Junction before being subsumed into the Midland in 1871, and afterwards remained known as the "Old" M&SWJ to distinguish it from the later line elsewhere in the country :-) Nick -- Serendipity: http://www.leverton.org/blosxom (last update 29th March 2010) "The Internet, a sort of ersatz counterfeit of real life" -- Janet Street-Porter, BBC2, 19th March 1996 |
#18
![]() |
|||
|
|||
![]()
On May 30, 5:27*am, Paul Corfield wrote:
I don't know where 2016 comes from - no one has posted any sort of timeline for electrifying the GOBLIN other than the link from Hornsey down to the MML as part of the Thameslink programme. This assumes the depot is still going to be at Hornsey after all of the NIMBY attacks. I pulled 2016 out of a hat - it seemed like as good a starting date as any. I like the 172s - as Mr Tolley says they are clean, well presented and run well enough on the line. *It is a shame that are still so many speed restrictions due to knackered infrastructure despite years of closures and engineering works that I had foolishly assumed would fix these issues. Ridership is way up based on my own observations. All stations are well used despite the alleged "non connectivity" with other lines. People seem to be able to find the line perfectly well. *As I said in another post peak trains leave Gospel Oak full with it being standing room only from Upper Holloway which is a busy stop. *Large numbers use South Tottenham and Blackhorse Road. I am less familiar with the eastern section of the line. *I have used the line far more this year than I have in the preceeding 3 or 4 years because the service is reliable and now frequent. Off peak services can load well too. That's very interesting. I wonder if these users are attracted solely by the Overground brand or if they are attracted by both the brand and the increased service levels. The only thing that really annoys me are the shoddy connections to and from the NLL at Gospel Oak where several times an hour trains on one line arrive as the other departs which is simply infuriating. Silverlink may have operated less frequently but there were planned connections rather than having doors shut in your face and being forced to wait 10 - 15 minutes for a "connection". *I know this would probably be "paradise" for people elsewhere in the country but Londoners tend to be pretty impatient when used to tube like connections of only a couple of minutes. Agreed. I wonder if this will improve once all of the signalling works are bedded in and a few timetable changes are made on the back of "breaking in" the new infrastructure elsewhere on the NLL and ELL. |
#19
![]() |
|||
|
|||
![]()
On May 31, 5:36*pm, Arthur Figgis wrote:
On 30/05/2011 11:47, Paul Corfield wrote: There are not enough 378s around nor are there any contract options left to be activated. I suspect that by the time comes around to electrify the line that Bombardier will have thrown away the jigs and People often say thrown away jigs will stop rolling stock orders, but what does it actually mean in the contect of modern trains? Won't they just upload computer files to a new jig-o-matic, or something? The problem is that doing that upload translates into a substantial lead time, since the work required to adjust the manufacturing equipment (including the jigs) so that it turns out the correct components and structural pieces means that it isn't cost-effective to do so for a small order. The first couple of pieces are unlikely to be quite right, and therefore you need to make enough of them to ensure that you get the correct pieces for later assembly. If the jigs and other systems needed to build 378s are in fact discarded and need to be reconstutited, TfL would have to order at least 10-15 4-car units in order to make it cost-effective. If the GOBLIN were electrified I'm not sure it could absorb 10-15 dual- voltage units all by itself, which means that TfL needs to use them somewhere else on the Overground, such as one of the core service routes (Willesden-Stratford, Clapham-Willesden, Highbury-West Croydon). |
#20
![]() |
|||
|
|||
![]()
On 31/05/2011 22:36, Arthur Figgis wrote:
On 30/05/2011 11:47, Paul Corfield wrote: There are not enough 378s around nor are there any contract options left to be activated. I suspect that by the time comes around to electrify the line that Bombardier will have thrown away the jigs and People often say thrown away jigs will stop rolling stock orders, but what does it actually mean in the contect of modern trains? Won't they just upload computer files to a new jig-o-matic, or something? Jigs are expensive bits of kit, probably cost as much as a complete train, you need a reasonably large order to make it worth while building them. Also they take up space that is probably now being used for a different project. -- Graeme Wall This account not read, substitute trains for rail. Railway Miscellany at www.greywall.demon.co.uk/rail |
Reply |
Thread Tools | Search this Thread |
Display Modes | |
|
|
![]() |
||||
Thread | Forum | |||
GOBLIN: FURTHER ELECTRIFICATION WORK. | London Transport | |||
Goblin to close for Electrification work | London Transport | |||
Goblin electrification | London Transport | |||
Goblin electrification | London Transport | |||
Goblin electrification | London Transport |