Home |
Search |
Today's Posts |
![]() |
|
London Transport (uk.transport.london) Discussion of all forms of transport in London. |
Reply |
|
|
LinkBack | Thread Tools | Display Modes |
|
#1
![]() |
|||
|
|||
![]()
Recliner wrote:
Roland Perry wrote: In message -sept ember.org, at 20:27:59 on Tue, 26 Apr 2016, Recliner remarked: I don't believe that absurdly low cost figure. In 1992 terms, the cost of the full Piccadilly line extension, including the four stations, was probably well over £250m, maybe closer to £500m. If you don't accept the contemporaneous figure of £26m build cost when it opened, then other discussion is futile. Can you come up with a better figure from the archives - if you do we can resume talking about the return on investment. As you well know, it wasn't a contemporaneous figure. It was an absurdly low estimate, from an aviation magazine, from years earlier, that was not only many times too small for even the original simple 1977 extension, but also couldn't have taken into account the eventual scope of the project, with four stations rather than two, and the extended tunnels to T4 and T5. £26m is in the right ballpark. According to Hansard from 15 Dec 1976 Mr. Sillars asked the Secretary of State for Transport what is his latest estimate of the Government share of costs associated with building the Piccadilly underground line extension to Heathrow Airport. Mr. William Rodgers - My Department contributed 25 per cent. of the total expenditure of £18.5 million incurred up to 31st March 1975. Expenditure since then, estimated at £7.2 million to 31st December 1976, qualifies under the Local Government Act 1974 for transport supplementary grant at the rate of 70 per cent. The total cost of the work outstanding at 31st December 1976 is estimated to be £3.6 million. http://hansard.millbanksystems.com/w...761215_CWA_194 So the total cost was approx 18.5 + 7.2 + 3.6 = 29.3 million. Using RPI, that would be around £220 million in todays money. Peter Smyth |
#2
![]() |
|||
|
|||
![]()
Peter Smyth wrote:
Recliner wrote: Roland Perry wrote: In message -sept ember.org, at 20:27:59 on Tue, 26 Apr 2016, Recliner remarked: I don't believe that absurdly low cost figure. In 1992 terms, the cost of the full Piccadilly line extension, including the four stations, was probably well over £250m, maybe closer to £500m. If you don't accept the contemporaneous figure of £26m build cost when it opened, then other discussion is futile. Can you come up with a better figure from the archives - if you do we can resume talking about the return on investment. As you well know, it wasn't a contemporaneous figure. It was an absurdly low estimate, from an aviation magazine, from years earlier, that was not only many times too small for even the original simple 1977 extension, but also couldn't have taken into account the eventual scope of the project, with four stations rather than two, and the extended tunnels to T4 and T5. £26m is in the right ballpark. According to Hansard from 15 Dec 1976 Mr. Sillars asked the Secretary of State for Transport what is his latest estimate of the Government share of costs associated with building the Piccadilly underground line extension to Heathrow Airport. Mr. William Rodgers - My Department contributed 25 per cent. of the total expenditure of £18.5 million incurred up to 31st March 1975. Expenditure since then, estimated at £7.2 million to 31st December 1976, qualifies under the Local Government Act 1974 for transport supplementary grant at the rate of 70 per cent. The total cost of the work outstanding at 31st December 1976 is estimated to be £3.6 million. http://hansard.millbanksystems.com/w...761215_CWA_194 So the total cost was approx 18.5 + 7.2 + 3.6 = 29.3 million. Using RPI, that would be around £220 million in todays money. Of course that was for the original two-station extension, but it nevertheless seems very low (and presumably doesn't include anything for the several additional trains needed for the extension, but presumably ordered in anticipation). What was the total cost including the two separate, subsequent extensions for T4 and T5, the latter also requiring a new grade-separated underground junction for the T4 and T5 lines to the west of the T123 station? Those extensions would certainly have much more than doubled the total cost. |
#3
![]() |
|||
|
|||
![]()
In message
-sept ember.org, at 22:18:44 on Wed, 27 Apr 2016, Recliner remarked: Mr. William Rodgers - My Department contributed 25 per cent. of the total expenditure of £18.5 million incurred up to 31st March 1975. Expenditure since then, estimated at £7.2 million to 31st December 1976, qualifies under the Local Government Act 1974 for transport supplementary grant at the rate of 70 per cent. The total cost of the work outstanding at 31st December 1976 is estimated to be £3.6 million. http://hansard.millbanksystems.com/w...761215_CWA_194 So the total cost was approx 18.5 + 7.2 + 3.6 = 29.3 million. Using RPI, that would be around £220 million in todays money. Of course that was for the original two-station extension, but it nevertheless seems very low (and presumably doesn't include anything for the several additional trains needed for the extension, but presumably ordered in anticipation). Tube lines have fleets of identical trains, you can't just order a few more later. What was the total cost including the two separate, subsequent extensions for T4 and T5, the latter also requiring a new grade-separated underground junction for the T4 and T5 lines to the west of the T123 station? Those extensions would certainly have much more than doubled the total cost. And generate double the fares. -- Roland Perry |
#4
![]() |
|||
|
|||
![]()
Roland Perry wrote:
In message -sept ember.org, at 22:18:44 on Wed, 27 Apr 2016, Recliner remarked: Mr. William Rodgers - My Department contributed 25 per cent. of the total expenditure of £18.5 million incurred up to 31st March 1975. Expenditure since then, estimated at £7.2 million to 31st December 1976, qualifies under the Local Government Act 1974 for transport supplementary grant at the rate of 70 per cent. The total cost of the work outstanding at 31st December 1976 is estimated to be £3.6 million. http://hansard.millbanksystems.com/w...761215_CWA_194 So the total cost was approx 18.5 + 7.2 + 3.6 = 29.3 million. Using RPI, that would be around £220 million in todays money. Of course that was for the original two-station extension, but it nevertheless seems very low (and presumably doesn't include anything for the several additional trains needed for the extension, but presumably ordered in anticipation). Tube lines have fleets of identical trains, you can't just order a few more later. Do you really think that? I must be imagining the extra train ordered for the Met to cover the Watford Junction extension, the extra carriages and trains ordered for the Jubilee line (even after the original UK factory that assembled them had closed), the extra carriages and trains ordered for the Overground, the extra carriages and Pendolino trains ordered for Virgin (also after the UK assembly plant had closed), the pending order for new Northern line trains for the Battersea extension, etc. But in this case, the 73TS were built while the Heathrow extension was under construction, and a large enough fleet to cover it was ordered. Without that extension, the order would have been for a significantly smaller fleet. They were later modified to have more luggage space by the doors, with fewer seats. What was the total cost including the two separate, subsequent extensions for T4 and T5, the latter also requiring a new grade-separated underground junction for the T4 and T5 lines to the west of the T123 station? Those extensions would certainly have much more than doubled the total cost. And generate double the fares. Probably not double (have you seen how few people use the T4 station?), but more certainly. But if you're going to estimate that total incremental revenue (as you did), then you also have to look at the total investment. |
#5
![]() |
|||
|
|||
![]()
In message
-sept ember.org, at 08:03:57 on Thu, 28 Apr 2016, Recliner remarked: the 73TS were built while the Heathrow extension was under construction, and a large enough fleet to cover it was ordered. Without that extension, the order would have been for a significantly smaller fleet. They were later modified to have more luggage space by the doors, with fewer seats. What was the total cost including the two separate, subsequent extensions for T4 and T5, the latter also requiring a new grade-separated underground junction for the T4 and T5 lines to the west of the T123 station? Those extensions would certainly have much more than doubled the total cost. And generate double the fares. Probably not double (have you seen how few people use the T4 station?), but more certainly. Latest annual station usage stats: T123 7.49m T5 3.90m T4 2.35m But if you're going to estimate that total incremental revenue (as you did), then you also have to look at the total investment. To simplify things I've only been looking at the cost, and revenue of, Phase 1, for most of the thread now. -- Roland Perry |
#6
![]() |
|||
|
|||
![]()
Roland Perry writes:
In message -sept ember.org, at 08:03:57 on Thu, 28 Apr 2016, Recliner remarked: Probably not double (have you seen how few people use the T4 station?), but more certainly. Latest annual station usage stats: T123 7.49m T5 3.90m T4 2.35m T123 serves 3 terminals, so assuming it represents equal numbers of passengers using each terminal, there is not much difference between 2.49m passengers using the station for access to each of terminals 1, 2 and 3 and the 2.35m who use the T4 station. |
#7
![]() |
|||
|
|||
![]()
Graham Murray wrote:
Roland Perry writes: In message -sept ember.org, at 08:03:57 on Thu, 28 Apr 2016, Recliner remarked: Probably not double (have you seen how few people use the T4 station?), but more certainly. Latest annual station usage stats: T123 7.49m T5 3.90m T4 2.35m T123 serves 3 terminals, so assuming it represents equal numbers of passengers using each terminal, there is not much difference between 2.49m passengers using the station for access to each of terminals 1, 2 and 3 and the 2.35m who use the T4 station. Three terminals? No Heathrow station serves more than two terminals. Not lately. As a hint, it's no longer called T123 station. |
#8
![]() |
|||
|
|||
![]() |
#9
![]() |
|||
|
|||
![]()
In message , at 18:40:42 on Thu,
28 Apr 2016, Graham Murray remarked: Probably not double (have you seen how few people use the T4 station?), but more certainly. Latest annual station usage stats: T123 7.49m T5 3.90m T4 2.35m T123 serves 3 terminals, There's only two at the moment. so assuming it represents equal numbers of passengers using each terminal, there is not much difference between 2.49m passengers using the station for access to each of terminals 1, 2 and 3 and the 2.35m who use the T4 station. Not sure what your point is - other than perhaps all the terminals get quite a lot of passengers. -- Roland Perry |
#10
![]() |
|||
|
|||
![]()
Roland Perry wrote:
In message -sept ember.org, at 08:03:57 on Thu, 28 Apr 2016, Recliner remarked: the 73TS were built while the Heathrow extension was under construction, and a large enough fleet to cover it was ordered. Without that extension, the order would have been for a significantly smaller fleet. They were later modified to have more luggage space by the doors, with fewer seats. What was the total cost including the two separate, subsequent extensions for T4 and T5, the latter also requiring a new grade-separated underground junction for the T4 and T5 lines to the west of the T123 station? Those extensions would certainly have much more than doubled the total cost. And generate double the fares. Probably not double (have you seen how few people use the T4 station?), but more certainly. Latest annual station usage stats: T123 7.49m T5 3.90m T4 2.35m But if you're going to estimate that total incremental revenue (as you did), then you also have to look at the total investment. To simplify things I've only been looking at the cost, and revenue of, Phase 1, for most of the thread now. Costs and revenues in current money terms? But I'm not sure you can separate them anyway: the central station is served by trains using all three phases of the project. |
Reply |
|
Thread Tools | Search this Thread |
Display Modes | |
|
|
![]() |
||||
Thread | Forum | |||
Heathrow runway will create £16bn | London Transport | |||
Heathrow runway will create £16bn | London Transport | |||
Heathrow runway will create £16bn | London Transport | |||
Heathrow runway will create £16bn | London Transport | |||
Heathrow runway will create £16bn | London Transport |