Home |
Search |
Today's Posts |
![]() |
|
London Transport (uk.transport.london) Discussion of all forms of transport in London. |
Reply |
|
LinkBack | Thread Tools | Display Modes |
#21
![]() |
|||
|
|||
![]()
Roland Perry wrote:
In message , at 13:01:35 on Fri, 6 Jul 2018, Anna Noyd-Dryver remarked: Right, here’s some Actual Facts copied from another forum. quote As I understand it, it was loss of all signalling power to Streatham Junction Remote Interlocking area. Ex-Southern Region area signalling installations usually have three seperate incoming power supply sources, but in this case there was a catastrophic failure of a part of common equipment. Other sources state that NR has had to bypass the equipment in hard wiring to get it working again, but before it could do that it first had to determine what had caused the original failure, and also monitor the temporary setup to make sure a hidden fault didn't reoccur and cause even more damage. I wonder what it was - they'd have pretty quickly been able to eliminate back-hoes, smoking substations, and National Grid technicians with finger trouble. From the end of my post: “Signal power feed triple redundant 3 input BUT the changeover swiitch (single point of failure) was what burnt out” Apparently the incident is subject to a formal inquiry which will report back to the NR Board and the DfT. Edit to add: This just in from GTR journeycheck: “The electrical supply that maintains this areas signalling system failed. The failure has been traced to a faulty power supply cable which feeds off the national grid.” Well, that must of given the changeover switchgear a good bang /quote And from another post in the same place: “Signal power feed triple redundant 3 input BUT the changeover swiitch (single point of failure) was what burnt out” That confirms everything I was saying about the cause, thanks. It appears to differ from Network Rail's originally announced quick-fix of generators, unless that's what they used ahead of working out it was safe to hard-wire one of the two remaining grid feeds. Thus they still have quite a big project ahead of them - reinstating the three-way failover equipment (as well as the grid having to make 3/3 rather than 2/3 of the supplies operational). It also confirms that it’s local equipment, not at the signalling centre itself. "A generator has been sourced to isolate the power feed and is expected to arrive at the signalling centre later this morning. Once the generator arrives, the situation will be re-assessed." So it's just a co-incidence that the signalling centre still had power, yet they needed to locate a generator there to re-energise the local equipment? Or that you/we are being over-specific about the terminology used in a statement that’s probably third-hand when it gets published by someone who’s not technical staff; and the generator is actually at the site in Streatham where the problem seems to have occurred, rather than at Three Bridges ROC which controls the area. Anna Noyd-Dryver |
#22
![]() |
|||
|
|||
![]()
In message , at 14:33:57 on Fri, 6 Jul 2018,
Anna Noyd-Dryver remarked: Roland Perry wrote: In message , at 13:01:35 on Fri, 6 Jul 2018, Anna Noyd-Dryver remarked: Right, here’s some Actual Facts copied from another forum. quote As I understand it, it was loss of all signalling power to Streatham Junction Remote Interlocking area. Ex-Southern Region area signalling installations usually have three seperate incoming power supply sources, but in this case there was a catastrophic failure of a part of common equipment. Other sources state that NR has had to bypass the equipment in hard wiring to get it working again, but before it could do that it first had to determine what had caused the original failure, and also monitor the temporary setup to make sure a hidden fault didn't reoccur and cause even more damage. I wonder what it was - they'd have pretty quickly been able to eliminate back-hoes, smoking substations, and National Grid technicians with finger trouble. From the end of my post: “Signal power feed triple redundant 3 input BUT the changeover swiitch (single point of failure) was what burnt out” I meant - what caused it to burn out? Just old age, or was it my suggestion that when one of the grid feeds failed for a random reason (they do, which is why one has three) the subsequent load via two of the contacts on the contact breakers was too high? Apparently the incident is subject to a formal inquiry which will report back to the NR Board and the DfT. Edit to add: This just in from GTR journeycheck: “The electrical supply that maintains this areas signalling system failed. The failure has been traced to a faulty power supply cable which feeds off the national grid.” Well, that must of given the changeover switchgear a good bang /quote And from another post in the same place: “Signal power feed triple redundant 3 input BUT the changeover swiitch (single point of failure) was what burnt out” That confirms everything I was saying about the cause, thanks. It appears to differ from Network Rail's originally announced quick-fix of generators, unless that's what they used ahead of working out it was safe to hard-wire one of the two remaining grid feeds. Thus they still have quite a big project ahead of them - reinstating the three-way failover equipment (as well as the grid having to make 3/3 rather than 2/3 of the supplies operational). It also confirms that it’s local equipment, not at the signalling centre itself. "A generator has been sourced to isolate the power feed and is expected to arrive at the signalling centre later this morning. Once the generator arrives, the situation will be re-assessed." So it's just a co-incidence that the signalling centre still had power, yet they needed to locate a generator there to re-energise the local equipment? Or that you/we are being over-specific about the terminology used in a statement that’s probably third-hand when it gets published by someone who’s not technical staff; and the generator is actually at the site in Streatham where the problem seems to have occurred, rather than at Three Bridges ROC which controls the area. Perhaps it's a case of over-reading "signalling centre" to mean "ROC", when what they mean is a portacabin on the trackside somewhere in Stretham. ps Kudos for being the first person to note the ROC isn't in Stretham. -- Roland Perry |
#23
![]() |
|||
|
|||
![]()
On 2018-07-06 15:05:43 +0000, Roland Perry said:
In message , at 14:33:57 on Fri, 6 Jul 2018, Anna Noyd-Dryver remarked: Roland Perry wrote: In message , at 13:01:35 on Fri, 6 Jul 2018, Anna Noyd-Dryver remarked: Right, here’s some Actual Facts copied from another forum. quote As I understand it, it was loss of all signalling power to Streatham Junction Remote Interlocking area. Ex-Southern Region area signalling installations usually have three seperate incoming power supply sources, but in this case there was a catastrophic failure of a part of common equipment. Other sources state that NR has had to bypass the equipment in hard wiring to get it working again, but before it could do that it first had to determine what had caused the original failure, and also monitor the temporary setup to make sure a hidden fault didn't reoccur and cause even more damage. I wonder what it was - they'd have pretty quickly been able to eliminate back-hoes, smoking substations, and National Grid technicians with finger trouble. From the end of my post: “Signal power feed triple redundant 3 input BUT the changeover swiitch (single point of failure) was what burnt out” I meant - what caused it to burn out? Just old age, or was it my suggestion that when one of the grid feeds failed for a random reason (they do, which is why one has three) the subsequent load via two of the contacts on the contact breakers was too high? We had an incident not long ago during an electrical refurbishment where, IIRC, the main switch "fell apart". It took several days for a replacement to be sourced from abroad (Germany, I think) and during that time a major site ran on generators (parts of it didn't run at all for some of the time). Sam -- The University of Edinburgh is a charitable body, registered in Scotland, with registration number SC005336. |
Reply |
Thread Tools | Search this Thread |
Display Modes | |
|
|
![]() |
||||
Thread | Forum | |||
Signal Failure | London Transport | |||
Piccadilly line signal failure | London Transport | |||
Signal failure on the central line? | London Transport | |||
How can you have a signal failure on an ATO system? | London Transport | |||
Why can't LU cope with a signal failure? | London Transport |