Home |
Search |
Today's Posts |
![]() |
|
London Transport (uk.transport.london) Discussion of all forms of transport in London. |
Reply |
|
LinkBack | Thread Tools | Display Modes |
#1
![]() |
|||
|
|||
![]()
Croxley Rail Link - Position Update October 2007
The Croxley Rail Link continues to be progressed by Hertfordshire County Council and remains one of the Council's identified Major Schemes within the Local Transport Plan 2006/7- 2010/11, for which it is seeking grant funding from DfT. It is very unusual for a County Council to act as a lead partner promoting such a railway scheme. We are leading because of the continuing changes of fortunes and structures within the rail industry and TFL. This produces the double challenge of leading a project in an arena for which we do not have the primary responsibility and in an arena which is subject to continuous change. The project was identified as a Priority 1A scheme within the Regional Transport Priorities and has been included within the Regional Funding Allocation programme for funding in the period 2009/10 to 2015/16. Whilst this overall funding time frame appears lengthy, placing the delivery of Croxley Rail Link within it is realistic, given that the scheme still has to be taken through a Transport & Works Act (TWA) process to secure the powers to construct. HCC are currently working with consultants toward production of 'Major Scheme Business Case' for submission to the Department of Transport to seek 'Programme Entry' status for the project. This is effectively an updated resubmission of previous bids, taking account of some specific queries DfT have raised regarding cost updates and clarification of risk allowances, in line with their recently revised guidance for bids of this nature. Through previous bid submissions to DfT and through negotiations with London Underground (LU) it has been previously established that: The scheme meets all the necessary economic criteria of DfT and TfL has approved the economic appraisal for the scheme. The Mayor of London has demonstrated support for the scheme and has publicly committed a funding contribution to the project of some £17m. TfL is prepared to formally enter a promotion agreement with Hertfordshire County Council to co-promote the Transport & Works Application Programme Entry (PE) status at this stage is required to reduce risk in the proposed delivery timetable. To achieve an opening date within the Regional Transport Priority funding window, the project needs to be granted PE as soon as possible by DfT as PE provides the trigger for the TWA process - HCC cannot advance a TWA process without an 'intention to fund' decision from DfT. Following recent discussions, DfT have sought to revisit some core assumptions around the project, and clarification of their requirements has led to some delay in the bid preparation, but HCC anticipate making a submission to DfT before the end of the calendar year. Under their new guidance, DfT have indicated that a decision on the granting of PE status will be forthcoming within 26 weeks. A possible timetable for the Project from that point forward is as follows: Summer 2008 Programme Entry Granted TWA Application Summer 2009 TWA Inquiry Autumn 2009 SoS Decision Summer 2010 Start On Site Summer 2012 Scheme Opening Summer 2014 .................................................. ................... .................................................. ................... John Burke WRUG |
#2
![]() |
|||
|
|||
![]() "burkey" wrote in message ups.com... Croxley Rail Link - Position Update October 2007 The Croxley Rail Link continues to be progressed by Hertfordshire County Council and remains one of the Council's identified Major Schemes within the Local Transport Plan 2006/7- 2010/11, for which it is seeking grant funding from DfT. Summer 2008 Programme Entry Granted TWA Application Summer 2009 TWA Inquiry Autumn 2009 SoS Decision Summer 2010 Start On Site Summer 2012 Scheme Opening Summer 2014 .................................................. ................... .................................................. ................... John Burke WRUG Wow, 7 years from now and goodness knows how long since the scheme was first proposed 400 yards of railway will have been built and the Met line will run into Watford Junc. What would all those consultants do without schemes like this. Mind you with Thames link started and Crossrail given the go ahead I suppose they have to latch onto something. Kevin |
Reply |
Thread Tools | Search this Thread |
Display Modes | |
|
|
![]() |
||||
Thread | Forum | |||
An open letter regarding Croxley Rail link | London Transport | |||
Manufacturing Gateway Gothenburg, Sweden. 19-21 October 2007 | London Transport | |||
Croxley Rail Link Petition | London Transport | |||
CROXLEY RAIL LINK - POSITION UPDATE - February 2007 | London Transport | |||
Future is bleak for Croxley Rail Link | London Transport |